VoteMarinaCA.org
Follow the evidence. Verify the source.

Provide comments, corrections or updates

Help improve the accuracy and completeness of VoteMarinaCA.org.

Quick reading tip: The first part of each section gives the main point. Extra tables and source details are there if you want to check the numbers.
Quick mobile view: This page starts with the main facts and keeps the source links available. Detailed models and wider research tables are easier to examine on a larger screen.
Construction cost and present worth
Fire station planning context
Fire station planning context
City Hall planning context
City Hall planning context
Current police facility and future planning context
Current police facility and future planning context

Why a $50 million gap can grow over time

The central distinction is between today's residual funding requirement and the amount that may actually be needed when construction contracts are awarded years later.

Construction cost escalation / project delivery
Construction cost escalation / project delivery. Replace this image with a licensed photo or document image.

Visual evidence

Images are supplemental. The factual claims on this page are intended to remain traceable to the primary-source links below.

The City's three-number breakdown

Total program
$69.25M
Current estimated total cost.
Identified funding
−$19.3M
Existing grants, impact fees and other sources.
Current gap
≈$50M
Approximately $49.98M in the June analysis.
Future gap
≈$58M
Estimated at construction after escalation and inflation.
$58M is not added on top of $69.25M; it is the estimated future funding gap after the existing resources are accounted for.
Data table 1
ComponentAmountMeaning
Total facility program$69.25MCurrent estimated total cost of the three priority facilities.
Existing/identified funding−≈$19.3MFunding already identified through grants, impact fees and other sources; not assumed to be unrestricted.
Current residual gap≈$49.98MApproximately $50M required based on the June 2026 estimate.
Estimated construction-time gap≈$58MCity's July 2026 estimate after anticipated construction-cost increases and inflation.

Example 3-year escalation of $50M

Data table 2
Annual escalation3-year resultIncrease over $50M
5.0%≈$57.88M≈$7.88M
5.2%≈$58.24M≈$8.24M
5.5%≈$58.73M≈$8.73M
6.0%≈$59.55M≈$9.55M

What-if illustration only. Actual construction escalation depends on timing, bid conditions, design changes, labor/material costs and procurement.

Why the City also talks about $58 million

The simplest way to read the City's documents is: $69.25M is the total facility program; approximately $19.3M is already identified; approximately $50M is the current residual gap; and approximately $58M is the City's estimated construction-time gap. The $58M figure should not be added to $69.25M or treated as a second $58M project.

Pay as you go: the cost of building one facility at a time

Waiting does not hold today’s price. If Marina had to assemble a replacement revenue stream and build the fire station first, City Hall second, and the police station last, each unbuilt facility would continue to rise in cost while the City saved for it.

Simple result: Under this conservative scenario, the three-facility program takes about 29 years to complete and costs about $130.3 million. That is about $61.1 million more than the $69.25 million planning baseline. The police station, built last, experiences the largest increase.

Assumptions used

Illustrative pay-as-you-go assumptions
InputValueWhy it is used
Starting identified resources$19.30MCity’s stated grants, impact fees, reserves, and other identified sources. Restrictions still apply.
New annual money available$3.83M each yearSame scale as the City’s estimated annual Measure Q revenue, but treated here as a hypothetical replacement from delayed programs, other revenue, grants, or a mix. No such City plan is currently adopted.
Annual revenue growth0%Keeps the accumulation estimate conservative and easy to follow.
Annual construction escalation4.0%Construction-specific planning assumption supported by the benchmarks below. It is not a forecast.
Build orderFire → City Hall → PoliceThe sequence requested for this scenario. A different order changes which building absorbs the longest delay.

How the facility baseline is divided: The CFCAC cost table showed $16.0M for Fire, $21.5M for City Hall, and $17.5M for Police, plus up to $6.0M for land acquisition. Applying the City table’s 15% construction adjustment produces $18.40M, $24.725M, and $20.125M. This scenario places the $6.0M land allowance with the first public-safety phase because the site must be secured before the Fire build. The three values total the City’s $69.25M planning baseline. This allocation is a website modeling choice, not a City-approved phasing budget.

What happens to each facility

Sequential construction at 4% annual escalation
FacilityPlanning baselineFunds become sufficientCost when builtIncrease from waitingCumulative construction paid
Fire station and shared public-safety site$24.40MYear 2$26.39M+$1.99M$26.39M
City Hall and Council Chambers$24.73MYear 13$41.17M+$16.44M$67.56M
Police station$20.12MYear 29$62.76M+$42.64M$130.32M
Total program$69.25MCompleted in Year 29$130.32M+$61.07M$130.32M
Total money assembled and sequential facility construction over 29 years The horizontal axis shows years zero through thirty. The vertical axis shows millions of dollars. Total resources begin at 19.3 million dollars and rise by 3.83 million dollars each year. Construction payments occur in year two for the fire station and shared site, year thirteen for City Hall, and year twenty-nine for the police station. Pay as you go requires more money because unbuilt facilities keep escalating $0M$20M$40M$60M$80M$100M$120M$140M 051015202530 Years after the planning baseline Total money, millions Total funds assembled Construction paid Fire: Y2City Hall: Y13Police: Y29
The blue line shows all resources assembled, including the initial $19.3M. The brown steps show construction payments. This is a website scenario, not the City’s adopted capital plan.

Where the 4% escalation assumption comes from

  • Marina’s own ENR adjustment: a City staff report documented a 4.17% one-year increase in the ENR index used for Marina’s impact-fee updates.
  • ENR’s latest annual readings: ENR reported its Building Cost Index rose 4.2% and its Construction Cost Index rose 3.6% during 2025. The BCI includes skilled construction labor.
  • California cross-check: the California Department of General Services builds its California Construction Cost Index from ENR Building Cost Index readings for San Francisco and Los Angeles.
  • Regional planning cross-check: San Francisco proposed 4.5% for its 2026 annual infrastructure construction-cost inflation estimate.

City of Marina ENR adjustment report · ENR 1Q 2026 cost report · California DGS CCCI · San Francisco 2026 construction inflation estimate · CFCAC facility-cost tables

Limits: This does not predict what Marina will do if Measure Q fails. The $3.83M annual replacement stream is hypothetical, the $19.3M includes funds with different restrictions, and final project scopes, land costs, bid timing, and grants could change. The calculation shows the compounding cost of delay under stated assumptions.

The City itself documents the escalation mechanism

This page is no longer based only on a hypothetical what-if table. The City's July 2026 announcement states that the three priority facilities were approximately $69M in the prior estimate, about $19.3M was already identified, leaving roughly $50M, while construction was not expected to begin for about three years and the estimated construction-time need was approximately $58M because of construction-cost increases and inflation.

Read the City’s July 2026 explanation ↗

What the $58 million means

  • It is not $58M of new borrowing automatically required today.
  • It is a estimated construction-time need.
  • The existing ≈$19.3M resources are already part of the funding picture.
  • The model must not add inflation twice - once to the total project cost and again to the residual funding gap.

The site therefore shows $50M as the approximate current residual funding requirement and ≈$58M as the City's estimated construction-time gap, while retaining the City's stated ≈$69M total project estimate and ≈$19.3M identified resources as the breakdown.

Escalation does not stop when the first building starts

The City's ≈$58M figure is a estimated construction-time funding gap, not a guarantee that the entire three-building program can still be delivered for $58M regardless of schedule. If design, bidding and construction stretch over many years, the unbuilt portions remain exposed to labor, materials and contractor-cost escalation.

5 percent construction escalation across a twenty-year build cycle
5% is a what-if assumption for long-run modeling. The City's June 2026 analysis used a separate 15% inflation adjustment assuming construction begins in 2027; the City's July explanation then estimated the current ≈$50M gap to ≈$58M by the time construction occurs.
Avoid double counting. The City's $69.25M March/June project estimate already included its stated 15% inflation assumption for a 2027 start. The site's 5% curve is applied prospectively to illustrate additional delay beyond the selected baseline, not added retroactively to costs that already include escalation.

Why assume construction costs will rise?

The escalation analysis is not based on ordinary consumer inflation alone. Marina itself has used the Engineering News-Record (ENR) Construction Cost Index to update development impact fees for construction inflation since 2016. The City's 2022 annual adjustment provides a concrete local example: the ENR index used by Marina rose from 12,647.32 in November 2021 to 13,174.98 in November 2022 - 4.17% in one year.

City of Marina - Development Impact Fees Study Update ↗
City of Marina - 2022 ENR adjustment report (4.17%) ↗

California also maintains its own California Construction Cost Index (CCCI) through the Department of General Services. DGS explains that CCCI is derived from ENR Building Cost Index values for San Francisco and Los Angeles. That makes it a useful California-specific cross-check rather than relying only on a national inflation measure.

California DGS - California Construction Cost Index ↗
Engineering News-Record - Construction Economics and index method ↗

Data table 3
Evidence / benchmarkWhat it showsHow this site uses it
Marina ENR indexing policyCity has indexed development impact fees to ENR construction costs since 2016.Establishes that construction-specific inflation is already part of Marina's own financial method.
Marina Nov. 2021 → Nov. 2022 ENR values12,647.32 → 13,174.98, a 4.17% annual increase.Provides a documented Marina-specific historical comparison to the site's 5% what-if rate.
California DGS CCCICalifornia index based on ENR San Francisco and Los Angeles BCI data.Provides a California-specific independent construction-cost benchmark.
ENR CCI / BCITracks construction labor and material components rather than general consumer prices.Supports using a construction index when discussing delayed building and improvement projects.
City's 2026 facilities estimate≈$69M program estimate, ≈$19.3M identified, ≈$50M current gap; City projects ≈$58M needed when construction begins after approximately three years.The City's own ≈$50M → ≈$58M estimate is displayed separately from this site's long-run 5% what-if model.
Important distinction: the website's 5% annual escalation rate is a what-if assumption, not an ENR forecast and not a claim that California construction costs will rise exactly 5% every year. It is close to Marina's documented 4.17% ENR increase for one recent historical year and is used to demonstrate compounding risk. Readers can compare it directly with the City's own ≈$50M-to-≈$58M construction-time estimate and the California DGS index.

The three facilities in the sequential model

1. Fire Station

Current Marina fire/public safety facility

First priority in this pay-as-you-go scenario.

2. City Hall / Council Chambers

Current Marina City Hall

Second priority in this scenario.

3. Police Station

Current Marina police/public safety facility

Third priority in this scenario.

Official photographs are sourced from the City of Marina facilities galleries. See graphics/FACILITY_PHOTO_SOURCES.txt for source pages and the local filenames to use when uploading the final photo files.

Why a $50 million bond and a $58 million future gap are different

The City's July 2026 explanation says the current gap is about $50M, construction is not expected to begin for approximately three years, and the estimated gap at construction is about $58M because of escalation and inflation.

Current and estimated construction funding gap
If the UUT supports approximately $50M of bond capacity while the construction-time gap is approximately $58M, roughly $8M still has to be bridged by other resources, cost reductions, later funding, or a combination.

The City's current FAQ says it will continue pursuing grants and external funding and that additional impact fees and other funding sources may be used as available. That is evidence of a continuing funding strategy, but it is not a published commitment to deposit a fixed amount of General Fund money into facility reserves every year.

For scale only, bridging $8M evenly across three years is approximately $2.67M per year. That arithmetic is not the City's adopted annual set-aside plan; no fixed three-year reserve schedule was located in the records reviewed.

Website correction: the prior $9.65M/year “savings” proxy has been removed. It incorrectly treated the full $19.3M mix of reserves, impact fees, grants and other funding as though it were a repeatable annual City savings rate.

City July 9, 2026 explanation of $50M current gap → ≈$58M construction-time gap ↗ · City ballot-measure FAQ on grants, impact fees and $50M money raised-bond capacity ↗

How do other City issues fit?

Parks, Preston Park, development incentives, litigation, recreation facilities and transportation projects can be legitimate questions without necessarily being the same financial question as Measure Q. Use the City Issues & Measure Q FAQ to see what is directly related, indirectly related, or financially separate.